The internal audit wing of the National Highways Department has reported that 70% of the construction works on the Avinashi Road flyover are complete, with the remainder expected to be finished by December. The project aims to alleviate traffic congestion on Avinashi Road. The team conducted vibration tests and assessed the structural stability of the construction. Works on the up and down ramps are progressing at seven locations.